Clearances

The Office of Environmental Health and Safety (OEH&S) must to be contacted for radiation, biological, and chemical clearances. The Business Manager of the Department in which the project is based should initiate this process and deliver the space to the constructor with all clearances in place. Construction activity cannot commence until all clearances are in hand. The Project Manager will initiate a hazardous material survey through a request to the Office of Environmental Health and Safety and, if asbestos or lead containing materials are discovered, will facilitate its removal.