Construction Closeout

Overview

Construction Closeout is the time period from Substantial Completion until all punch list items have been addressed and are completed. The Constructor finishes all remaining items and completes all final invoices for the work.

Punchlist

On the date of Substantial Completion a Punch list is complied by walking through the completed project to check for those outstanding items which are contractually owed and have not been completed. The user should attend the walk through with the Team to review the project and add items to the punchlist as necessary. It should be noted that at this time only those items which are contractually owed and have not been completed are to be put on the Punchlist. This is not an opportunity to add scope to the project.